I-405 UPDATE: Lane, ramp closures through April 9

Published 4:52 pm Friday, April 2, 2010

The Washington state Department has posted the following Interstate 405 construction updates through Friday, April 9.

The nighttime Benson Road closures are continuing as part of the Stage 2 I-405 project to add a half-diamond interchange at Talbot and the freeway.

Closure information changes frequently, so check for updatesthroughout the week.

Highlights this week include:

• Up to three lanes in both directions of I-405 from I-5 to SR 167 will close nightly, Saturday – Thursday from 9 p.m. to 5 a.m.

• Up to two lanes in both directions of I-405 from SR 167 to SR 169 will close nightly, Monday – Thursday from 9 p.m. to 4:30 a.m.

• Benson Road South between City Hall and Eagle Ridge Drive in Renton will close each weeknight, Monday – Friday from 8 p.m. to 5 a.m.

• Up to three lanes on southbound I-405 from Southeast Eighth Street to I-90 in Bellevue will close nightly, Monday – Thursday from 8 p.m. 5 a.m. to install pavement markings. This work is weather dependent.

• The on- ramp from Southeast Eighth Street to southbound I-405 and the off-ramp to Southeast Eighth Street from southbound I-405 in Bellevue will close nightly, Monday – Thursday from 8 p.m. to 5 a.m. to install pavement markings. This work is weather dependent.

• The on-ramp from Northeast Fourth Street to southbound I-405 in Bellevue will close nightly, Monday – Thursday, from 11 p.m. to 5 a.m. to install pavement markings.

• The on-ramp from westbound SR 520 to southbound I-405 will close nightly, Monday – Thursday from 10 p.m. to 4 a.m. for construction work.

• Up to two lanes in both directions of I-405 from Northeast 195th Street to SR 527 will close nightly, Monday – Thursday from 9 p.m. to 5:30 a.m.