Some erosion occurring in soil that supports Howard Hanson Dam on Green River

Some erosion is occurring in the soil abutment that supports the right side of Howard Hanson Dam, which controls the flow of the Green River, the latest testing by the U.S. Army Corps of Engineers shows.

The federal agency has been closely monitoring and studying the dam for several months after two depressions opened on the dam’s right abutment during the mid-January floods.

Any undermining of the earth and rock abutment, the product of a 10,000-year-old landslide, could cause water to flow through and around the structure, potentially weakening it and the dam itself.

The corps has warned there is an increased chance of winter flooding of the Green, with runs through south Renton. Such flooding could reach deep into the low-lying parts of the city and force evacuations to higher ground. The City of Renton is coordinating with other agencies a regional response to such widespread flooding.

The City of Renton was told of the recent findings this week, according to city spokeswoman, Preeti Shridhar.

“We didn’t see any major changes in the situation,” she said.

During testing last week, the pool behind the dam reached an elevation of 1,169.2 feet, when engineers saw renewed reasons to believe that the abutment is still weakened, according to an agency news release.

Of particular concern is the recent dye testing that shows that water is moving through the right abutment very fast at higher pool elevations, according to the news release.

These tests indicate that there are preferential flow paths within the natural materials of the right abutment that could lead to internal erosion within the right abutment if water is held at these higher elevations for extended periods of time, according to the agency.

“This phenomenon continues to be troubling,” said Mamie Brouwer, program manager. There is, however, no visible distress of the right abutment has been observed, she said.

Although data collected below 1,157 feet seems to stay within normal ranges, elevations going higher seem to cause more seepage and uncertain water paths through the abutment.

Therefore, according to the news release, the corps has decided to release water from the dam over the course of the next two weeks, to bring the pool level down to 1,155 feet above sea level. This operation will result in reservoir outflows that are not expected to exceed 1,200 cubic feet per second based on current weather and hydrologic forecasts, which is within established thresholds. Residents along the river will not see significant changes in the river flows over the next two weeks

Around-the-clock monitoring continues, as will other data-collection processes during the pool draft.

“We do not understand how the water is traveling through the abutment,” Brouwer said. “We know that what we may be seeing fits the traditional definition of internal erosion.”

The Seattle District’s immediate objective is preparing for the upcoming fall/winter flood season. Preparations include continuing with plans to construct an interim seepage barrier wall and improving the drainage tunnel to control seepage through the most critical part of the right abutment, and continuing to monitor the pool throughout the draft. Simultaneously, the team has initiated test borings, geotechnical modeling and analysis to support planning for a long term repair project to address seepage.

Meanwhile the Seattle District Commander, Col. Anthony O. Wright, wants the downstream community residents to know that the risk for higher flood levels is significantly increased compared to what they are typically used to, until such time as the issues with the dam’s right abutment can be resolved.

“I can’t stress enough our number one mission here is public safety,” Wright said. “We will continue to keep Green River Valley leaders and first responders informed. We ask that residents contact their community leaders and get as much information as possible on how to prepare for such a contingency.”

Wright was referring to the corps’ efforts of working closely with King County and the downstream cities of Auburn, Kent, Renton and Tukwila to prepare for the fall/winter flood season with the increased risk of higher-than-standard flows from the dam.

“Regardless of the possibility of increased flow rates from the dam,” said Dam Safety Program Manager, Rob Romocki, “It truly is important for the communities to understand that this is a river valley and the potential for flooding exists even when Howard Hanson Dam has full operational capacity and the levees work as they should. So, it’s easy to see the risk increasing when the dam has a lowered operational capacity.”