Engineers try to get ahead of construction smell in Renton

Large wastewater treatment pipe project underway, could cause an odor

Editor’s note: a previous version of this story had the wrong number of years that the South Treatment Plant in Renton has been in permit compliance. It has been updated.

The sewage pipe project on Logan Avenue North might get smelly soon, but it’s not too likely.

After several weeks of prepping the site, which closed the intersection of Burnett Avenue North and North Sixth Street, the project will start pumping millions of gallons of wastewater that goes through the Eastside Interceptor, above ground in a temporary pressurized bypass.

Meanwhile, the interceptor, an eight-foot corroded sewage pipe that carries wastewater from the Eastside cities under Logan Avenue, will be repaired to extend the life of the pipe.

Because of its size it would be nearly impossible to replace due to the size of the line and disruption it would cause, which is why it’s being restored.

The bypass is scheduled to start running June 17, Stantec Project Manager and Principal Chris Ruiz said.

At that point, he said, that’s when odor would be most obvious. That’s why there are specific odor control facilities in place. One includes a misting facility which acts like rain to knock down pollution and tamp down odor, which can cover a broad area.

The bypass pumping will then continue until mid-October.

Stantec is a global firm, with an office located in Bellevue and is leading construction management of the interceptor project. The team at the office consists of environmental engineers, geologists and surveyors, and rehabilitate sewers, according to the company’s website.

Ruiz has been with the Bellevue office for 20 years and said this will be his largest underground project to-date.

“The key is to have all your ducks lined in a row and be ready to execute a well-written plan,” Ruiz said, adding they’ve been preparing since October.

At the May 20 Renton City Council Meeting, Vice President of the North Renton Neighborhood Association Nora Schultz said there have been a few bumps in the road.

“I don’t think this project was on anyone’s bucket list,” Schultz said.

But Schultz said the neighborhood association appreciated King County’s attempts to reach out to residents.

The project is going smoothly so far and they are trying to be great neighbors to the Landing, Boeing and residents.

“We’re taking all of their comments to heart and trying to address them usually within 24 hours,” Ruiz said.

One example Ruiz gave was one noise complaint from a resident. He said they just asked the contractor to do the saw-cutting earlier in the day.

King County Wastewater Treatment Division spokesperson Norm Mah stated in an email that there’s hasn’t been any issues related to an increased need for noise or odor controls.

The project has a noise variance that allows them to work around the clock, except for Sundays. But Ruiz said he still wants to make sure they’re within the working hours. The current schedule looks like 7 a.m. to 7 p.m., with some work underground at night.

Inspectors will be onsite 24/7 in the event of damage to the pipe or the possibility of being overwhelmed with heavy rainfall. The inspector can then take immediate action to shut down the bypass, Ruiz said.

According to a weekly update provided through King County, the crews are finishing melding the temporary bypass. There will be multi-lane night closures from now until early June and a few temporary bus stop closures at North 10th Street and Logan Avenue North.

The bike lane along Logan Avenue North is also closed between Park Avenue North and North Sixth Street.

Burnett Avenue North will remain closed for the duration of most of the project, the Renton Reporter previously reported.

There’s a lot of steps involved in prepping the line; making sure the bypass can hold 45 million gallons a day and strong enough to withstand the pressure, and then to hold up against outside conditions.

The top of the eight-foot sewer pipe has been exposed, but required careful inspection, being so close to the Burlington Northern Railroad tracks.

After that, electrical pumps keeping the sewage moving require its own temporary power and backup systems. Then crews need to test it all before taking the interceptor out of service.

There will be three crews down in the interceptor pipe, and a few inspectors above ground.

Most of the bypass is above ground, but some street intersections and Boeing driveways required shallow excavation so the line could be buried below and covered with steel plates or asphalt, Ruiz said.

At the end of the project, Ruiz said they will restore the roadways, sidewalks, crosswalk markings or signage, curbing, gutters and landscapes disrupted.

“Everything will be restored to the previous condition or better,” he said.

This interceptor is critical to the King County sewage system, which recently received an award for the South Treatment Plant in Renton and the Vashon Treatment Plant.

King County’s Wastewater Treatment Division recently won Peak Performance awards from the National Association of Clean Water Agencies for “outstanding compliance,” according to a press release from the wastewater treatment division.

The South Treatment Plant, where the wastewater in the Eastside Interceptor flows to, has received 100 percent permit compliance for 21 years, according to the press release.

The county disinfects nearly 200 million gallons of wastewater for about 1.7 million people in the greater Puget Sound region every day.

The county also sends out weekly newsletters about the project, which people can subscribe to here.

More in News

File photo
$30 car tab proposal returns to ballot in November

Tim Eyman-led initiative would restrict car tabs and transportation benefit districts in Washington.

File photo
King County alcohol production ordinance could be approved by year’s end

Update to county code has been more than a year in the making.

Bring Fido and a can of food to support local animal shelters

“You Lucky Dog!” is more than an expression, it’s an event in… Continue reading

Renton Schools Foundation to host gala

To celebrate 10 years and welcome a new executive director, the Renton… Continue reading

Carol Ann Witschi
Witschi’s seat to stay vacant till election

Renton City Council has decided to leave councilmember Carol Ann Witschi’s seat… Continue reading

Photo by Haley Ausbun. Faith-Maria, a third grader at St. Anthony Elementary School in Renton, asked Make-a-Wish to share her wish with her school, which resulted in two new smart boards. Faith-Maria with her family at the unveiling, Sept. 12.
A selfless wish for Renton schools

Faith-Maria Nguyen uses Make-A-Wish to provide school a smart board

Photo by Haley Ausbun. RESP union members attended the Sept. 11 Renton School Board meeting to make their story heard as they continue to negotiate for a new contract with the district.
Union leader: ‘Give us what we deserve’

Update: Paraprofessionals and staff have reached a tentative agreement with the Renton School District

Photo by Haley Ausbun. Photo left to right: David Rodriguez, Tony Ventrella, Rachel Chronister, Marla Veliz, Reagan Dunn, and Gavin Hunt at the Sept. 10 ribbon cutting for the New Horizon School van, gifted by King County Councilmember Reagan Dunn through the retired van program.
County van to increase New Horizon’s inclusivity

A vehicle gifted to a school for students with learning disabilities will support outreach

Photo by Haley Ausbun. Tiffany Park Elementary School teachers and parents hold up signs before the Sept. 11 Renton School Board meeting, over the loss of a fourth grade classroom that reorganized the fourth and fifth graders at the school.
Teacher changes shake up parents’ confidence in Renton schools

A quick staffing change and classroom switch has parents questioning Renton School District

Most Read